
|
7/23/2007
South End Elementary School
Intersection of Iranistan Avenue & University Avenue
The concrete work for the new gymnasium is in progress. Work continues on the reinforcing for the existing concrete floor slabs. Abatement of the lead paint has started. Work on the new roof has begun. Interior partitions on all floors is under way. Mechanical and electrical work is in progress on all floors.
|

Enlarge
|
|
7/20/2007
Cesar A. Batalla Elementary School
Intersection of State Street & Howard Avenue
On May 8, 2007 the Cesar A. Batalla Elementary School was awarded the Award of Merit for K-12 schools by the Connecticut Building Congress.
|

Enlarge
|
|
6/6/2007
South End Elementary School
Intersection of Iranistan Avenue & University Avenue
Interior demolition is 90% complete. Contractors are currently working on removing the existing roof as well as installing HVAC and plumbing. Excavation for the gymnasium is ongoing.
|
|
|
4/5/2007
South End Elementary School
Intersection of Iranistan Avenue & University Avenue
Asbestos abatement is approximately 75 - 80 % complete. Soft demolition 60% complete and hard demolition will begin next week.
|

Enlarge
|
|
10/9/2006
North End Elementary School
Intersection of North Avenue & Lexington Avenue
Demolition has been completed. Bids have been received. Construction Manager is performing scope reviews with contractors & providing the City with Letters of Recommendations.
|
|
|
5/17/2006
JFK Academic
700 Palisades Avenue
New handicap accessible shower in boys locker/pool room
|

Enlarge
|
|
4/27/2006
North End Elementary School
Intersection of North Avenue & Lexington Avenue
Looking along North Ave. at apartment buildings being prepared for demolition
|

Enlarge
|
|
4/27/2006
North End Elementary School
Intersection of North Avenue & Lexington Avenue
Looking down towards the corner of Chestnut & James Street at demolished foundations
|

Enlarge
|
|
3/14/2006
South End Elementary School
Intersection of Iranistan Avenue & University Avenue
Design work is in progress for the future Swing Space and South End School
|
.jpg)
Enlarge
|
|
3/14/2006
North End Elementary School
Intersection of North Avenue & Lexington Avenue
Demolition to start late March 2006. Construction bidding to start early May 2006.
|
|
|
9/1/2005
Cesar A. Batalla Elementary School
Intersection of State Street & Howard Avenue
Steel Erection is proceeding 3 weeks ahead of schedule. Concrete foundation work, underground rough-in and concrete slabs are also in progress ahead of schedule.
|

Enlarge
|
|
9/1/2005
Bassick High School
1181 Fairfield Avenue
The new elevator pit along with a new handicap accessible Nurse's Suite are preceding this summer.
|

Enlarge
|
|
9/1/2005
Harding High Schoo
1734 Central Avenue
Locker Room handicap sink work along with audible fire alarm and accessible science room work stations are proceeding this summer.
|

Enlarge
|
|
7/11/2005
Cesar A. Batalla Elementary School
Intersection of State Street & Howard Avenue
Construction started in May 2005, concrete foundation work is currently in progress and structural steel erection is scheduled to start in August 2005.
|

Enlarge
|
|
7/11/2005
North End Elementary School
Intersection of North Avenue & Lexington Avenue
Design work is expected to be completed in August 2005, demolition work is expected to start late summer 2005 and construction to start winter
2005/2006.
|
|
|
7/11/2005
Jettie S. Tisdale Elementary School
Intersection of Hollister Street & Carrie Street
Design work is expected to be completed in December 2005, demolition is expected to start in January 2006 and construction to start Summer 2006.
|
|
|
7/11/2005
New Barnum Elementary School
Intersection of Hallett Street & Martin Luther King Drive
Design work is expected to be completed in November 2005 and construction is expected to start late Spring 2006.
|
|
|
6/30/2005
Blackham Elementary School
425 Thorme Street
ADA upgrades include accessible restrooms and locker rooms, accessible work stations in academic rooms, improved access to the Health Suite, accessible seating in the gym, wheelchair lift to stage, and ADA compliant hardware in designated classrooms.
|
|
|
6/30/2005
Central High School
1 Lincoln Boulevard
ADA upgrades include accessible restrooms and locker rooms, accessible work stations in academic rooms, accessible seating in the main gym, wheelchair lift to the auditorium stage and to the music room risers, and ADA compliant hardware in designated classrooms.
|
|
|
6/30/2005
Harding High Schoo
1734 Central Avenue
ADA upgrades include accessible restrooms and locker rooms, accessible work stations in academic rooms, accessible seating in the main gym and auditorium, wheelchair lift to the stage, and ADA compliant hardware in designated classrooms.
|
|
|
6/30/2005
JFK Academic
700 Palisades Avenue
ADA upgrades include accessible restrooms and locker rooms, accessible work stations in academic rooms, wheelchair lift to stage, and ADA compliant hardware in designated classrooms.
|
|
|
6/30/2005
Luis Munoz Marin School
479 Helen Street
ADA upgrades include accessible restrooms and locker rooms, accessible work stations in academic rooms, improved access to the Health Suite, accessible seating in the gym, wheelchair lift to the stage, and ADA compliant hardware in designated classrooms.
|
|
|
6/29/2005
Bassick High School
1181 Fairfield Avenue
ADA upgrades include a new elevator that will make all floors in the original building accessible. Work also includes accessible restrooms and locker rooms, a wheelchair lift to the stage, accessible work stations in academic rooms, accessible seating in the main gym and auditorium, and ADA compliant hardware in designated classrooms.
|
|
|
|
 |
 |
 |