| Students: |
|
750 |
| Size: |
|
105,000 sq. ft. |
| Estimated Occupancy: |
|
COMPLETED August 2008 |
| |
|
|
Updates:
|
|
7/11/2005 Design work is expected to be completed in August 2005, demolition work is expected to start late summer 2005 and construction to start winter
2005/2006.
|
3/13/2006 Abatement work is proceeding |
3/14/2006 Project sign now in place |
|
3/14/2006 Demolition to start late March 2006. Construction bidding to start early May 2006. |
4/27/2006 Location of demolished apartment buildings along Chestnut Street |
4/27/2006 Heavy Equipment used in the demolition and foundation removal |
4/27/2006 Looking along North Ave. at apartment buildings being prepared for demolition |
4/27/2006 Looking down towards the corner of Chestnut & James Street at demolished foundations |
7/19/2006 All buildings have been demolished at the North End School site. |
|
10/9/2006 Demolition has been completed. Bids have been received. Construction Manager is performing scope reviews with contractors & providing the City with Letters of Recommendations. |
1/19/2007 Common building interior footings |
1/19/2007 James Street Entrance |
3/26/2007 Underground Plumbing in Commons Building |
3/26/2007 Steel erection at Commons Building Area |
6/6/2007 Academic "B" Wing |
6/6/2007 Gym Decking |
7/20/2007 Exterior of Media Center |
7/20/2007 Main Entrance in Progress |
9/7/2007 North Side of Academic Wing |
9/7/2007 East Side of Commons Building |
12/27/2007 Installation of Exterior Masonry |
12/27/2007 Window Installation in Progress |
4/23/2008 Exterior Landscaping in progress |
4/23/2008 Academic Wing Entrance |
4/23/2008 Building Exterior |
9/8/2008 Main Entrance |
9/8/2008 New Gym with Climbing Walls |
9/8/2008 New Library Media Center |
9/8/2008 2nd Grade Classroom set-up |