Jettie S. Tisdale Elementary School 250 Hollister Avenue
7/11/2005Design work is expected to be completed in December 2005, demolition is expected to start in January 2006 and construction to start Summer 2006.
3/14/2006Demolition bidding in progress. Construction bidding to start early June 2006.
5/26/2006Construction of new bus loop
5/26/2006New fencing around the construction site
7/13/2006demoliton in progress
7/13/2006Lead abatement work in progress
9/7/2006Looking South between Logan & Hewitt
9/7/2006Tank Removal & Soil Remediation at 218 Hollister
10/9/2006New School Project Sign
10/25/2006Official ground breaking on October 23, 2006
10/25/2006Ground breaking for the new Jettie S. Tisdale Elementary School
1/19/2007Installation of UG Plumbing
1/19/2007Water proofing the elevator pit
3/26/2007Preparation for slab on decking
3/26/2007Exterior wall framing
6/6/2007Gym walls are going up
6/6/2007Main Corridor
7/20/2007Duck Work & Mechanical Piping
7/20/2007Brick & Block Veneer in Progress
9/7/2007Sidewalk work in progress
9/7/2007Drywall Progress
12/27/2007Installation of Athletic Equipment
12/27/2007Landscaping in progress
12/27/2007Installation of classroom millwork
4/23/2008New Gymnasium
4/23/2008Cafeteria & Auditorium Combined
4/23/2008Computer Lab