Jettie S. Tisdale Elementary School

250 Hollister Avenue

  750
  105,000 sq. ft.
  COMPLETED April 2008
   
Updates:

7/11/2005
Design work is expected to be completed in December 2005, demolition is expected to start in January 2006 and construction to start Summer 2006.

3/14/2006
Demolition bidding in progress. Construction bidding to start early June 2006.

5/26/2006
Construction of new bus loop

5/26/2006
New fencing around the construction site

7/13/2006
demoliton in progress

7/13/2006
Lead abatement work in progress

9/7/2006
Looking South between Logan & Hewitt

9/7/2006
Tank Removal & Soil Remediation at 218 Hollister

10/9/2006
New School Project Sign

10/25/2006
Official ground breaking on October 23, 2006

10/25/2006
Ground breaking for the new Jettie S. Tisdale Elementary School

1/19/2007
Installation of UG Plumbing

1/19/2007
Water proofing the elevator pit

3/26/2007
Preparation for slab on decking

3/26/2007
Exterior wall framing

6/6/2007
Gym walls are going up

6/6/2007
Main Corridor

7/20/2007
Duck Work & Mechanical Piping

7/20/2007
Brick & Block Veneer in Progress

9/7/2007
Sidewalk work in progress

9/7/2007
Drywall Progress

12/27/2007
Installation of Athletic Equipment

12/27/2007
Landscaping in progress

12/27/2007
Installation of classroom millwork

4/23/2008
New Gymnasium

4/23/2008
Cafeteria & Auditorium Combined

4/23/2008
Computer Lab